Clearing the Corridor: To prepare the area for construction and to help clear any potential hazard trees that could cause outages, vegetation management crews will be cutting, trimming, and mowing within the corridor.
Rebuild: The Section 1 line that runs from a CMP substation in Augusta to Smiley Avenue in Winslow will be rebuilt with new, stronger, more storm-resilient steel poles.
Reroute: In Winslow, Section 40 from Smiley Avenue to Winslow Substation also will be rebuilt with steel poles. Beginning at Smiley Avenue, Section 1 will be rerouted onto the new Section 40 segment.
Decommission: The current Section 1 also travels from Smiley Avenue and runs parallel to Route 100 to Heywood Road and the Winslow Substation on Benton Avenue. Once the new line is energized, the existing structures will be removed. This will also be the case for the old section 1 in Augusta.
Tree work:
Vegetation clearing and mowing:
Matting:
Construction:
Structure Removal and Restoration:
Work for Section 1 is anticipated to take place between November 2024 and October 2026. Please visit the Construction Schedule page to see the sequence of work.
Crews may be working in an area, leave, and return at a later date depending on the nature of the work they are doing. Our work schedule may change due to poor weather conditions.
At CMP, safety is a priority – yours and our crews. Our easements will be active construction sites. Please do not enter. If you have any project-related questions, please contact Project Outreach at [email protected] or 888.267.0831.
Work activity will comply with town ordinances. Typical construction noise, including drilling and the operation of heavy equipment should be expected.
For more information about CMP’s Section 1 Transmission Line Rebuild, please contact Project Outreach