Work for the Section 1 project is anticipated to take place between November 2024 and October 2026.

The work will be completed in phases, beginning in Winslow and working towards Augusta.

Phase 1 – Fall 2024-Spring 2025

  • Tree cutting, trimming, and mowing from Winslow to Augusta

Phase 2 – Spring-Fall 2025

  • Installing Access Roads in Vassalboro and Augusta
  • Installing Matting from Winslow to Vassalboro
  • Remaining Mowing in Vassalboro and Augusta
  • Construction from Winslow to Vassalboro

Phase 3 – Fall 2025

  • Structure removal and restoration from Benton Avenue, Winslow to Bog Road, Vassalboro
  • Install matting from Vassalboro to Augusta

Phase 4 – Winter 2025-Spring 2026

  • Construction from Bog Road, Vassalboro to Church Hill Road, Augusta
  • Completing remaining tree work

Phase 5 – Spring-Summer 2026

  • Structure removal and restoration from Bog Road, Vassalboro to Church Hill Road, Augusta.
  • Construction from Church Hill Road, Augusta to Route 3, Augusta

Phase 6 – Fall 2026

  • Structure removal and restoration from Church Hill Road, Augusta to Route 3, Augusta.



 

Get in touch

For more information about CMP’s Section 1 Transmission Line Rebuild, please contact Project Outreach

T: 888-267-0821
E: [email protected]

Ask a question?

Name is a required field
Email is a required field
Street Address is a required field
Question is a required field