Construction Schedule

Work for the Section 1 project is anticipated to take place between Fall 2024 and Spring 2026.

Phase 1 – Fall 2024-Spring 2025

  • Tree cutting, trimming, and mowing from Winslow to Augusta

Phase 2 – Spring-Fall 2025

  • Installing Access Roads in Winslow and Vassalboro
  • Installing Matting from Winslow to Vassalboro
  • Construction from Winslow to Vassalboro
  • Additional crews mobilize, start construction at Augusta working north to Vassalboro

Phase 3 – Fall 2025

  • Complete construction from Winslow to Vassalboro
  • Additional crews complete construction and energize from Vassalboro to Augusta

Phase 4 – Winter 2025-Spring 2026

  • Structure removals starting in Augusta and working north
  • Remove all matting and complete restoration
  • Construction wrap up




 

Get in touch

For more information about CMP’s Section 1 Transmission Line Rebuild, please contact Project Outreach

T: 888-267-0821
E: [email protected]

Ask a question?

Name is a required field
Email is a required field
Street Address is a required field
Question is a required field